Project Start Date: Sat 7/12/03
Project Finish Date: Fri 11/21/03
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | Scope | 6.88 days | Sat 7/12/03 | Mon 7/14/03 | 99% | |
| 2 | Determine project scope | 4 hrs | Mon 7/14/03 | Mon 7/14/03 | Edmond Lau (M) | 100% |
| 3 | Secure project sponsorship | 2 hrs | Mon 7/14/03 | Mon 7/14/03 | Edmond Lau (M) | 100% |
| 4 | Define preliminary resources | 0 days | Sat 7/12/03 | Sat 7/12/03 | Edmond Lau (M) | 100% |
| 5 | Secure core resources | 0 days | Sat 7/12/03 | Sun 7/13/03 | Edmond Lau (M) | 100% |
| 6 | Scope complete | 0 days | Sun 7/13/03 | Sun 7/13/03 | 0% | |
| 7 | Analysis/Software Requirements | 15.75 days | Sat 7/12/03 | Thu 7/17/03 | 64% | |
| 8 | Conduct needs analysis | 0.88 days | Sat 7/12/03 | Sun 7/13/03 | Edmond Lau (A) | 100% |
| 9 | Draft preliminary software specifications | 3.75 days | Sat 7/12/03 | Mon 7/14/03 | Edmond Lau (A)[13%] | 100% |
| 10 | Develop preliminary budget | 2 hrs | Mon 7/14/03 | Mon 7/14/03 | Edmond Lau (M) | 100% |
| 11 | Review software specifications/budget with team | 5 hrs | Mon 7/14/03 | Tue 7/15/03 | D'laila Pereira,Edmond Lau (M) | 25% |
| 12 | Incorporate feedback on software specifications | 1 day | Tue 7/15/03 | Tue 7/15/03 | Edmond Lau (A) | 0% |
| 13 | Develop delivery timeline | 3 hrs | Wed 7/16/03 | Wed 7/16/03 | Edmond Lau (M) | 50% |
| 14 | Obtain approvals to proceed (concept, timeline, budget) | 8 hrs | Wed 7/16/03 | Thu 7/17/03 | Edmond Lau (M) | 0% |
| 15 | Secure required resources | 2 hrs | Thu 7/17/03 | Thu 7/17/03 | Edmond Lau (M) | 0% |
| 16 | Analysis complete | 0 days | Thu 7/17/03 | Thu 7/17/03 | 0% | |
| 17 | Design | 18 days | Thu 7/17/03 | Wed 7/23/03 | 44% | |
| 18 | Review preliminary software specifications | 1 day | Thu 7/17/03 | Thu 7/17/03 | Edmond Lau (A) | 80% |
| 19 | Develop functional specifications | 3.25 days | Thu 7/17/03 | Sat 7/19/03 | Edmond Lau (A) | 98% |
| 20 | Develop prototype based on functional specifications | 3 days | Sat 7/19/03 | Mon 7/21/03 | Edmond Lau (A) | 0% |
| 21 | Review functional specifications | 6 hrs | Mon 7/21/03 | Tue 7/22/03 | D'laila Pereira | 0% |
| 22 | Incorporate feedback into functional specifications | 1 day | Tue 7/22/03 | Wed 7/23/03 | Edmond Lau (M),D'laila Pereira[50%] | 0% |
| 23 | Obtain approval to proceed | 0 hrs | Wed 7/23/03 | Wed 7/23/03 | Edmond Lau (M),D'laila Pereira[50%] | 0% |
| 24 | Design complete | 0 days | Wed 7/23/03 | Wed 7/23/03 | 0% | |
| 25 | Development | 174.38 days | Wed 7/23/03 | Fri 9/19/03 | 0% | |
| 26 | Review functional specifications | 1 day | Wed 7/23/03 | Wed 7/23/03 | Edmond Lau | 0% |
| 27 | Identify modular/tiered design parameters | 1 day | Wed 7/23/03 | Thu 7/24/03 | Edmond Lau | 0% |
| 28 | Assign development staff | 1 day | Thu 7/24/03 | Thu 7/24/03 | Edmond Lau | 0% |
| 29 | Develop code | 138.38 days | Thu 7/24/03 | Mon 9/8/03 | Edmond Lau,Edmond Nolan[80%],M.N. Jagadeesh[40%],Hendrik Muller,Sergey Reznick | 0% |
| 30 | XML Standard (DTD / Schema) Development | 5 days | Thu 7/24/03 | Thu 7/31/03 | M.N. Jagadeesh | 0% |
| 31 | Qt Frontend Development | 5 days | Wed 8/13/03 | Tue 8/19/03 | Edmond Nolan[80%],Sergey Reznick,Hendrik Muller | 0% |
| 32 | Qt and C++ Backend Development | 26 days | Tue 8/19/03 | Mon 9/8/03 | Edmond Lau[50%],Edmond Nolan[80%],Sergey Reznick,Hendrik Muller | 0% |
| 33 | Develop code (prelimary testing) | 16.13 days | Mon 9/8/03 | Fri 9/19/03 | Edmond Lau[50%],Edmond Nolan[80%],M.N. Jagadeesh[40%],Hendrik Muller,Sergey Reznick | 0% |
| 34 | Development complete | 0 days | Fri 9/19/03 | Fri 9/19/03 | 0% | |
| 35 | Testing | 329.92 days | Wed 7/23/03 | Mon 11/10/03 | 0% | |
| 36 | Develop unit test plans using product specifications | 4 days | Wed 7/23/03 | Tue 7/29/03 | D'laila Pereira | 0% |
| 37 | Develop integration test plans using product specifications | 4 days | Wed 7/23/03 | Tue 7/29/03 | D'laila Pereira | 0% |
| 38 | Unit Testing | 117.67 days | Mon 9/22/03 | Fri 10/31/03 | 0% | |
| 39 | Review modular code | 6.25 days | Mon 9/22/03 | Tue 9/30/03 | Edmond Nolan[20%],M.N. Jagadeesh[60%] | 0% |
| 40 | Test component modules to product specifications | 4.55 days | Tue 9/30/03 | Mon 10/6/03 | M.N. Jagadeesh[60%],Edmond Nolan[20%] | 0% |
| 41 | Identify anomalies to product specifications | 6.25 days | Mon 10/6/03 | Wed 10/15/03 | M.N. Jagadeesh[60%],Edmond Nolan[20%] | 0% |
| 42 | Modify code | 6.25 days | Wed 10/15/03 | Thu 10/23/03 | M.N. Jagadeesh[60%],Edmond Nolan[20%] | 0% |
| 43 | Re-test modified code | 6.25 days | Thu 10/23/03 | Fri 10/31/03 | M.N. Jagadeesh[60%],Edmond Nolan[20%] | 0% |
| 44 | Unit testing complete | 0 days | Fri 10/31/03 | Fri 10/31/03 | 0% | |
| 45 | Integration Testing | 30 days | Fri 10/31/03 | Mon 11/10/03 | 0% | |
| 46 | Test module integration | 2.5 days | Fri 10/31/03 | Wed 11/5/03 | Edmond Nolan,Sergey Reznick | 0% |
| 47 | Identify anomalies to specifications | 1 day | Wed 11/5/03 | Thu 11/6/03 | Edmond Nolan,Sergey Reznick | 0% |
| 48 | Modify code | 1.5 days | Thu 11/6/03 | Fri 11/7/03 | Edmond Nolan,Sergey Reznick | 0% |
| 49 | Re-test modified code | 1 day | Fri 11/7/03 | Mon 11/10/03 | Edmond Nolan,Sergey Reznick | 0% |
| 50 | Integration testing complete | 0 days | Mon 11/10/03 | Mon 11/10/03 | 0% | |
| 51 | Training | 212.58 days | Wed 7/23/03 | Thu 10/2/03 | 0% | |
| 52 | Develop training specifications for end users | 2.63 days | Wed 7/23/03 | Fri 7/25/03 | Edmond Lau,D'laila Pereira[50%] | 0% |
| 53 | Develop training specifications for helpdesk support staff | 2.63 days | Wed 7/23/03 | Fri 7/25/03 | Edmond Lau,D'laila Pereira[50%] | 0% |
| 54 | Identify training delivery methodology (computer based training, classroom, etc.) | 5 hrs | Wed 7/23/03 | Thu 7/24/03 | D'laila Pereira | 0% |
| 55 | Develop training materials | 1 wk | Mon 9/22/03 | Fri 9/26/03 | M.N. Jagadeesh,D'laila Pereira,Hendrik Muller | 0% |
| 56 | Conduct training usability study | 1.33 days | Mon 9/29/03 | Tue 9/30/03 | M.N. Jagadeesh,Hendrik Muller,D'laila Pereira | 0% |
| 57 | Finalize training materials | 1 day | Tue 9/30/03 | Wed 10/1/03 | M.N. Jagadeesh,Hendrik Muller,D'laila Pereira | 0% |
| 58 | Develop training delivery mechanism | 1 day | Wed 10/1/03 | Thu 10/2/03 | Edmond Lau (M),D'laila Pereira | 0% |
| 59 | Training materials complete | 0 days | Thu 10/2/03 | Thu 10/2/03 | 0% | |
| 60 | Documentation | 102.04 days | Wed 7/23/03 | Tue 8/26/03 | 0% | |
| 61 | Develop Help specification | 0.33 days | Wed 7/23/03 | Wed 7/23/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 62 | Develop Help system | 1 wk | Mon 8/18/03 | Fri 8/22/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 63 | Review Help documentation | 1 day | Mon 8/25/03 | Mon 8/25/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 64 | Incorporate Help documentation feedback | 0.67 days | Tue 8/26/03 | Tue 8/26/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 65 | Develop user manuals specifications | 0.67 days | Wed 7/23/03 | Thu 7/24/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 66 | Develop user manuals | 1 wk | Mon 8/18/03 | Fri 8/22/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 67 | Review all user documentation | 0.67 days | Mon 8/25/03 | Mon 8/25/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 68 | Incorporate user documentation feedback | 0.67 days | Mon 8/25/03 | Tue 8/26/03 | M.N. Jagadeesh,Hendrik Muller,Sergey Reznick | 0% |
| 69 | Documentation complete | 0 days | Tue 8/26/03 | Tue 8/26/03 | 0% | |
| 70 | Pilot | 357.75 days | Thu 7/17/03 | Thu 11/13/03 | 0% | |
| 71 | Identify test group | 5 days | Thu 7/17/03 | Thu 7/24/03 | D'laila Pereira[20%] | 0% |
| 72 | Develop software delivery mechanism | 1 day | Thu 7/24/03 | Thu 7/24/03 | 0% | |
| 73 | Install/deploy software | 1 day | Mon 11/10/03 | Mon 11/10/03 | Edmond Lau | 0% |
| 74 | Obtain user feedback | 2.5 days | Tue 11/11/03 | Thu 11/13/03 | D'laila Pereira,Edmond Nolan | 0% |
| 75 | Evaluate testing information | 1 day | Thu 11/13/03 | Thu 11/13/03 | Edmond Lau | 0% |
| 76 | Pilot complete | 0 days | Thu 11/13/03 | Thu 11/13/03 | 0% | |
| 77 | Deployment | 13.13 days | Fri 11/14/03 | Tue 11/18/03 | 0% | |
| 78 | Determine final deployment strategy | 1 day | Fri 11/14/03 | Fri 11/14/03 | D'laila Pereira | 0% |
| 79 | Develop deployment methodology | 1 day | Mon 11/17/03 | Mon 11/17/03 | D'laila Pereira | 0% |
| 80 | Secure deployment resources | 0 days | Mon 11/17/03 | Mon 11/17/03 | Sergey Reznick | 0% |
| 81 | Train support staff | 0 days | Mon 11/17/03 | Mon 11/17/03 | Sergey Reznick | 0% |
| 82 | Deploy software | 1 day | Tue 11/18/03 | Tue 11/18/03 | Edmond Lau (M) | 0% |
| 83 | Deployment complete | 0 days | Tue 11/18/03 | Tue 11/18/03 | 0% | |
| 84 | Post Implementation Review | 7.13 days | Wed 11/19/03 | Fri 11/21/03 | 0% | |
| 85 | Document lessons learned | 1 day | Wed 11/19/03 | Wed 11/19/03 | D'laila Pereira | 0% |
| 86 | Distribute to team members | 1 day | Thu 11/20/03 | Thu 11/20/03 | D'laila Pereira | 0% |
| 87 | Create software maintenance team | 1 day | Fri 11/21/03 | Fri 11/21/03 | D'laila Pereira | 0% |
| 88 | Post implementation review complete | 0 days | Fri 11/21/03 | Fri 11/21/03 | 0% | |
| 89 | Software development template complete | 0 days | Fri 11/21/03 | Fri 11/21/03 | 0% |
| ID | Name | Group | Max Units | Peak Units |
|---|---|---|---|---|
| 1 | Management | 100% | 0% | |
| 2 | Project Manager | 100% | 0% | |
| 3 | Analyst | 100% | 0% | |
| 4 | Edmond Lau | Development Team | 100% | 300% |
| 5 | Testers | 100% | 0% | |
| 6 | Trainers | 100% | 0% | |
| 7 | Technical Communicators | 100% | 0% | |
| 8 | Deployment Team | 100% | 0% | |
| 9 | ||||
| 10 | ||||
| 11 | D'laila Pereira | Project Manager | 100% | 420% |
| 12 | Edmond Lau (M) | Management | 100% | 100% |
| 13 | Edmond Nolan | Development Team | 100% | 240% |
| 14 | M.N. Jagadeesh | Development Team | 100% | 240% |
| 15 | Hendrik Muller | Development Team | 100% | 500% |
| 16 | Sergey Reznick | Development Team | 100% | 500% |
| 17 | Edmond Lau (A) | Analyst | 100% | 100% |
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|---|---|---|---|---|---|
| 2 | Determine project scope | Edmond Lau (M) | 4 hrs | Mon 7/14/03 | Mon 7/14/03 | 100% |
| 3 | Secure project sponsorship | Edmond Lau (M) | 2 hrs | Mon 7/14/03 | Mon 7/14/03 | 100% |
| 4 | Define preliminary resources | Edmond Lau (M) | 0 hrs | Sat 7/12/03 | Sat 7/12/03 | 100% |
| 5 | Secure core resources | Edmond Lau (M) | 0 hrs | Sat 7/12/03 | Sun 7/13/03 | 100% |
| 8 | Conduct needs analysis | Edmond Lau (A) | 7 hrs | Sun 7/13/03 | Sun 7/13/03 | 100% |
| 9 | Draft preliminary software specifications | Edmond Lau (A) | 4 hrs | Sat 7/12/03 | Mon 7/14/03 | 100% |
| 10 | Develop preliminary budget | Edmond Lau (M) | 2 hrs | Mon 7/14/03 | Mon 7/14/03 | 100% |
| 11 | Review software specifications/budget with team | D'laila Pereira | 5 hrs | Mon 7/14/03 | Tue 7/15/03 | 0% |
| 11 | Review software specifications/budget with team | Edmond Lau (M) | 5 hrs | Mon 7/14/03 | Tue 7/15/03 | 50% |
| 12 | Incorporate feedback on software specifications | Edmond Lau (A) | 8 hrs | Tue 7/15/03 | Tue 7/15/03 | 0% |
| 13 | Develop delivery timeline | Edmond Lau (M) | 3 hrs | Wed 7/16/03 | Wed 7/16/03 | 50% |
| 14 | Obtain approvals to proceed (concept, timeline, budget) | Edmond Lau (M) | 8 hrs | Wed 7/16/03 | Thu 7/17/03 | 0% |
| 15 | Secure required resources | Edmond Lau (M) | 2 hrs | Thu 7/17/03 | Thu 7/17/03 | 0% |
| 18 | Review preliminary software specifications | Edmond Lau (A) | 8 hrs | Thu 7/17/03 | Thu 7/17/03 | 80% |
| 19 | Develop functional specifications | Edmond Lau (A) | 26 hrs | Thu 7/17/03 | Sat 7/19/03 | 98% |
| 20 | Develop prototype based on functional specifications | Edmond Lau (A) | 24 hrs | Sat 7/19/03 | Mon 7/21/03 | 0% |
| 21 | Review functional specifications | D'laila Pereira | 6 hrs | Mon 7/21/03 | Tue 7/22/03 | 0% |
| 22 | Incorporate feedback into functional specifications | Edmond Lau (M) | 4 hrs | Tue 7/22/03 | Wed 7/23/03 | 0% |
| 22 | Incorporate feedback into functional specifications | D'laila Pereira | 4 hrs | Tue 7/22/03 | Wed 7/23/03 | 0% |
| 23 | Obtain approval to proceed | Edmond Lau (M) | 0 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 23 | Obtain approval to proceed | D'laila Pereira | 0 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 26 | Review functional specifications | Edmond Lau | 8 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 27 | Identify modular/tiered design parameters | Edmond Lau | 8 hrs | Wed 7/23/03 | Thu 7/24/03 | 0% |
| 28 | Assign development staff | Edmond Lau | 8 hrs | Thu 7/24/03 | Thu 7/24/03 | 0% |
| 29 | Develop code | Edmond Lau | 1,107 hrs | Thu 7/24/03 | Mon 9/8/03 | 0% |
| 29 | Develop code | Edmond Nolan | 207.2 hrs | Thu 7/24/03 | Mon 9/8/03 | 0% |
| 29 | Develop code | M.N. Jagadeesh | 103.6 hrs | Thu 7/24/03 | Mon 9/8/03 | 0% |
| 29 | Develop code | Hendrik Muller | 259 hrs | Thu 7/24/03 | Mon 9/8/03 | 0% |
| 29 | Develop code | Sergey Reznick | 259 hrs | Thu 7/24/03 | Mon 9/8/03 | 0% |
| 30 | XML Standard (DTD / Schema) Development | M.N. Jagadeesh | 40 hrs | Thu 7/24/03 | Thu 7/31/03 | 0% |
| 31 | Qt Frontend Development | Edmond Nolan | 32 hrs | Wed 8/13/03 | Tue 8/19/03 | 0% |
| 31 | Qt Frontend Development | Sergey Reznick | 40 hrs | Wed 8/13/03 | Tue 8/19/03 | 0% |
| 31 | Qt Frontend Development | Hendrik Muller | 40 hrs | Wed 8/13/03 | Tue 8/19/03 | 0% |
| 32 | Qt and C++ Backend Development | Edmond Lau | 60 hrs | Tue 8/19/03 | Sun 8/24/03 | 0% |
| 32 | Qt and C++ Backend Development | Edmond Nolan | 96 hrs | Tue 8/19/03 | Mon 9/8/03 | 0% |
| 32 | Qt and C++ Backend Development | Sergey Reznick | 120 hrs | Tue 8/19/03 | Mon 9/8/03 | 0% |
| 32 | Qt and C++ Backend Development | Hendrik Muller | 120 hrs | Tue 8/19/03 | Mon 9/8/03 | 0% |
| 33 | Develop code (prelimary testing) | Edmond Lau | 40 hrs | Mon 9/8/03 | Thu 9/11/03 | 0% |
| 33 | Develop code (prelimary testing) | Edmond Nolan | 64 hrs | Mon 9/8/03 | Fri 9/19/03 | 0% |
| 33 | Develop code (prelimary testing) | M.N. Jagadeesh | 32 hrs | Mon 9/8/03 | Fri 9/19/03 | 0% |
| 33 | Develop code (prelimary testing) | Hendrik Muller | 80 hrs | Mon 9/8/03 | Fri 9/19/03 | 0% |
| 33 | Develop code (prelimary testing) | Sergey Reznick | 80 hrs | Mon 9/8/03 | Fri 9/19/03 | 0% |
| 36 | Develop unit test plans using product specifications | D'laila Pereira | 32 hrs | Wed 7/23/03 | Tue 7/29/03 | 0% |
| 37 | Develop integration test plans using product specifications | D'laila Pereira | 32 hrs | Wed 7/23/03 | Tue 7/29/03 | 0% |
| 39 | Review modular code | Edmond Nolan | 10 hrs | Mon 9/22/03 | Tue 9/30/03 | 0% |
| 39 | Review modular code | M.N. Jagadeesh | 30 hrs | Mon 9/22/03 | Tue 9/30/03 | 0% |
| 40 | Test component modules to product specifications | M.N. Jagadeesh | 8.73 hrs | Tue 9/30/03 | Thu 10/2/03 | 0% |
| 40 | Test component modules to product specifications | Edmond Nolan | 7.27 hrs | Tue 9/30/03 | Mon 10/6/03 | 0% |
| 41 | Identify anomalies to product specifications | M.N. Jagadeesh | 6 hrs | Mon 10/6/03 | Wed 10/8/03 | 0% |
| 41 | Identify anomalies to product specifications | Edmond Nolan | 10 hrs | Mon 10/6/03 | Wed 10/15/03 | 0% |
| 42 | Modify code | M.N. Jagadeesh | 6 hrs | Wed 10/15/03 | Thu 10/16/03 | 0% |
| 42 | Modify code | Edmond Nolan | 10 hrs | Wed 10/15/03 | Thu 10/23/03 | 0% |
| 43 | Re-test modified code | M.N. Jagadeesh | 6 hrs | Thu 10/23/03 | Fri 10/24/03 | 0% |
| 43 | Re-test modified code | Edmond Nolan | 10 hrs | Thu 10/23/03 | Fri 10/31/03 | 0% |
| 46 | Test module integration | Edmond Nolan | 20 hrs | Fri 10/31/03 | Wed 11/5/03 | 0% |
| 46 | Test module integration | Sergey Reznick | 20 hrs | Fri 10/31/03 | Wed 11/5/03 | 0% |
| 47 | Identify anomalies to specifications | Edmond Nolan | 8 hrs | Wed 11/5/03 | Thu 11/6/03 | 0% |
| 47 | Identify anomalies to specifications | Sergey Reznick | 8 hrs | Wed 11/5/03 | Thu 11/6/03 | 0% |
| 48 | Modify code | Edmond Nolan | 12 hrs | Thu 11/6/03 | Fri 11/7/03 | 0% |
| 48 | Modify code | Sergey Reznick | 12 hrs | Thu 11/6/03 | Fri 11/7/03 | 0% |
| 49 | Re-test modified code | Edmond Nolan | 8 hrs | Fri 11/7/03 | Mon 11/10/03 | 0% |
| 49 | Re-test modified code | Sergey Reznick | 8 hrs | Fri 11/7/03 | Mon 11/10/03 | 0% |
| 52 | Develop training specifications for end users | Edmond Lau | 8 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 52 | Develop training specifications for end users | D'laila Pereira | 8 hrs | Wed 7/23/03 | Fri 7/25/03 | 0% |
| 53 | Develop training specifications for helpdesk support staff | Edmond Lau | 8 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 53 | Develop training specifications for helpdesk support staff | D'laila Pereira | 8 hrs | Wed 7/23/03 | Fri 7/25/03 | 0% |
| 54 | Identify training delivery methodology (computer based training, classroom, etc.) | D'laila Pereira | 5 hrs | Wed 7/23/03 | Thu 7/24/03 | 0% |
| 55 | Develop training materials | M.N. Jagadeesh | 40 hrs | Mon 9/22/03 | Fri 9/26/03 | 0% |
| 55 | Develop training materials | D'laila Pereira | 40 hrs | Mon 9/22/03 | Fri 9/26/03 | 0% |
| 55 | Develop training materials | Hendrik Muller | 40 hrs | Mon 9/22/03 | Fri 9/26/03 | 0% |
| 56 | Conduct training usability study | M.N. Jagadeesh | 10.67 hrs | Mon 9/29/03 | Tue 9/30/03 | 0% |
| 56 | Conduct training usability study | Hendrik Muller | 10.67 hrs | Mon 9/29/03 | Tue 9/30/03 | 0% |
| 56 | Conduct training usability study | D'laila Pereira | 10.67 hrs | Mon 9/29/03 | Tue 9/30/03 | 0% |
| 57 | Finalize training materials | M.N. Jagadeesh | 8 hrs | Tue 9/30/03 | Wed 10/1/03 | 0% |
| 57 | Finalize training materials | Hendrik Muller | 8 hrs | Tue 9/30/03 | Wed 10/1/03 | 0% |
| 57 | Finalize training materials | D'laila Pereira | 8 hrs | Tue 9/30/03 | Wed 10/1/03 | 0% |
| 58 | Develop training delivery mechanism | Edmond Lau (M) | 8 hrs | Wed 10/1/03 | Thu 10/2/03 | 0% |
| 58 | Develop training delivery mechanism | D'laila Pereira | 8 hrs | Wed 10/1/03 | Thu 10/2/03 | 0% |
| 61 | Develop Help specification | M.N. Jagadeesh | 2.67 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 61 | Develop Help specification | Hendrik Muller | 2.67 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 61 | Develop Help specification | Sergey Reznick | 2.67 hrs | Wed 7/23/03 | Wed 7/23/03 | 0% |
| 62 | Develop Help system | M.N. Jagadeesh | 40 hrs | Mon 8/18/03 | Fri 8/22/03 | 0% |
| 62 | Develop Help system | Hendrik Muller | 40 hrs | Mon 8/18/03 | Fri 8/22/03 | 0% |
| 62 | Develop Help system | Sergey Reznick | 40 hrs | Mon 8/18/03 | Fri 8/22/03 | 0% |
| 63 | Review Help documentation | M.N. Jagadeesh | 8 hrs | Mon 8/25/03 | Mon 8/25/03 | 0% |
| 63 | Review Help documentation | Hendrik Muller | 8 hrs | Mon 8/25/03 | Mon 8/25/03 | 0% |
| 63 | Review Help documentation | Sergey Reznick | 8 hrs | Mon 8/25/03 | Mon 8/25/03 | 0% |
| 64 | Incorporate Help documentation feedback | M.N. Jagadeesh | 5.33 hrs | Tue 8/26/03 | Tue 8/26/03 | 0% |
| 64 | Incorporate Help documentation feedback | Hendrik Muller | 5.33 hrs | Tue 8/26/03 | Tue 8/26/03 | 0% |
| 64 | Incorporate Help documentation feedback | Sergey Reznick | 5.33 hrs | Tue 8/26/03 | Tue 8/26/03 | 0% |
| 65 | Develop user manuals specifications | M.N. Jagadeesh | 5.33 hrs | Wed 7/23/03 | Thu 7/24/03 | 0% |
| 65 | Develop user manuals specifications | Hendrik Muller | 5.33 hrs | Wed 7/23/03 | Thu 7/24/03 | 0% |
| 65 | Develop user manuals specifications | Sergey Reznick | 5.33 hrs | Wed 7/23/03 | Thu 7/24/03 | 0% |
| 66 | Develop user manuals | M.N. Jagadeesh | 40 hrs | Mon 8/18/03 | Fri 8/22/03 | 0% |
| 66 | Develop user manuals | Hendrik Muller | 40 hrs | Mon 8/18/03 | Fri 8/22/03 | 0% |
| 66 | Develop user manuals | Sergey Reznick | 40 hrs | Mon 8/18/03 | Fri 8/22/03 | 0% |
| 67 | Review all user documentation | M.N. Jagadeesh | 5.33 hrs | Mon 8/25/03 | Mon 8/25/03 | 0% |
| 67 | Review all user documentation | Hendrik Muller | 5.33 hrs | Mon 8/25/03 | Mon 8/25/03 | 0% |
| 67 | Review all user documentation | Sergey Reznick | 5.33 hrs | Mon 8/25/03 | Mon 8/25/03 | 0% |
| 68 | Incorporate user documentation feedback | M.N. Jagadeesh | 5.33 hrs | Mon 8/25/03 | Tue 8/26/03 | 0% |
| 68 | Incorporate user documentation feedback | Hendrik Muller | 5.33 hrs | Mon 8/25/03 | Tue 8/26/03 | 0% |
| 68 | Incorporate user documentation feedback | Sergey Reznick | 5.33 hrs | Mon 8/25/03 | Tue 8/26/03 | 0% |
| 71 | Identify test group | D'laila Pereira | 8 hrs | Thu 7/17/03 | Thu 7/24/03 | 0% |
| 73 | Install/deploy software | Edmond Lau | 8 hrs | Mon 11/10/03 | Mon 11/10/03 | 0% |
| 74 | Obtain user feedback | D'laila Pereira | 20 hrs | Tue 11/11/03 | Thu 11/13/03 | 0% |
| 74 | Obtain user feedback | Edmond Nolan | 20 hrs | Tue 11/11/03 | Thu 11/13/03 | 0% |
| 75 | Evaluate testing information | Edmond Lau | 8 hrs | Thu 11/13/03 | Thu 11/13/03 | 0% |
| 78 | Determine final deployment strategy | D'laila Pereira | 8 hrs | Fri 11/14/03 | Fri 11/14/03 | 0% |
| 79 | Develop deployment methodology | D'laila Pereira | 8 hrs | Mon 11/17/03 | Mon 11/17/03 | 0% |
| 80 | Secure deployment resources | Sergey Reznick | 0 hrs | Mon 11/17/03 | Mon 11/17/03 | 0% |
| 81 | Train support staff | Sergey Reznick | 0 hrs | Mon 11/17/03 | Mon 11/17/03 | 0% |
| 82 | Deploy software | Edmond Lau (M) | 8 hrs | Tue 11/18/03 | Tue 11/18/03 | 0% |
| 85 | Document lessons learned | D'laila Pereira | 8 hrs | Wed 11/19/03 | Wed 11/19/03 | 0% |
| 86 | Distribute to team members | D'laila Pereira | 8 hrs | Thu 11/20/03 | Thu 11/20/03 | 0% |
| 87 | Create software maintenance team | D'laila Pereira | 8 hrs | Fri 11/21/03 | Fri 11/21/03 | 0% |